Home BUSINESSAreva-Siemens demands 3.5b euros from TVO
Print
Sat, 25 Oct, 2014 12:01:36 AM
FTimes-STT Report, Oct 25
Olkiluoto 3 nuclear power plant unit at Olkiluoto.Photo – Lehtikuva.
Finnish nuclear power company Teollisuuden Voima Oyj (TVO) and nuclear supplier consortium Areva-Siemens have both updated cost estimates and losses caused by the delay in the Olkiluoto 3 nuclear power plant project, said TVO in a release.

Both parties have recently submitted the updated costs and loss estimates to the International Chamber of Commerce (ICC) arbitration proceedings.

The updated quantification submitted by Areva-Siemens on Friday totalled 3.5 billion euros. The sum includes over 1.3 billion euros in penalty interests calculated until October this year, payments allegedly delayed by TVO under the plant contract as well as approximately 150 million euros of alleged lost profit, said TVO.

TVO’s estimate of its costs and losses related to the arbitration proceedings is approximately 2.3 billion euros until the end of 2018.

TVO said it has previously considered the claims upon which the amounts demanded are based and found them to be of no merit.
 